Weather Fiji, Suva   Max 30°C, Min 23°C

Fiji Sun

NATION

Major Suva Bridges To Open From Next Week

Major Suva Bridges To Open From Next Week
The Vatuwaqa Bridge ready for opening. Photo: Vilimoni Vaganalau.
January 05
11:00 2018

 

The Vatuwaqa and Stinson Parade bridges will open to traffic on January 10 and January 11 respectively.

This was confirmed by Fiji Roads Authority chief executive officer Jonathan Moore.

“This is part of the Suva Arterial Road Upgrade Project (SARUP 1) that the contract is set up to improve the main arterial roads. We are reconstructing and upgrading the road,” Mr Moore said.

“This is a fully-programmed capital project. Our contractor for SARUP 1 is the China Railway Fifth Group.

“Once the project is completed, it will have an improved capacity, which will allow a balanced traffic-flow particularly during peak hours.”

 

Bridge update:

Vatuwaqa bridge- opening next week Wednesday

Stinson Parade Bridge- opening next week Thursday

Nabua Roundabouts – work in progress

 

Under SARUP 1 there are eight sections of roads include:

Queens Road (Tamavua-i-Wai bridge to lami Bridge) work will start this year

Edinburgh Drive (Walu Bay roundabout to FNU lights) work in progress

Ratu Mara Road (FNU lights to Lakeba Street lights) Work in progress

Kings Road A (Nabua round-about to Center point lights) Work in progress

Kings Road E (Center point lights to Kinoya lights) Work in progress

Kings Road B (Laqere lights to Makoi lights) Work in progress

MacArthur Street – Completed

Gaji Road- Work in progress

 

Edited by Ranoba Baoa

Feedback:  wati.talebula@fijisun.com.fj