Denarau Corporation Limited has issued a detailed temporary traffic plan as works on the $7.5 million Denarau Bridge construction continues. The re-direction traffic plan will be effective from July 3,
25 Jun 2015 12:29
Denarau Announces  New Traffic Plan
Traffic Re-direction plan
Denarau Corporation Limited has issued a detailed temporary traffic plan as works on the $7.5 million Denarau Bridge construction continues.

The re-direction traffic plan will be effective from July 3, Friday next week.

Information gathered from Denarau Corporation says the third phase of Denarau Bridge development is nearing completion.

Corporate Communications executive Leanne Edwards said: “We request all commuters to and from Denarau Island to take note of the plan.

“This is mainly on the temporary re-direction of traffic via the Bailey bridge. Drivers are required to adhere to the traffic diversions in place.”

The works are being carried out by contractors Pacific Marine & Civil Solutions (PMCS).

They are now working on the pedestrian walkway, which will also be carrying the temporary services lines.

Phase four with the temporary road installation is anticipated to be completed by next week when all traffic in and out of Denarau Island will be re-directed on the Bailey bridge.

Denarau bridge details on Development Phases

Phase 1: Works underway with the camp setup and will be followed by the Crane Pad on the North East side of the bridge site. During this phase there will be minimal disruption to the current flow of traffic. (Timeline: 1 month)

– Phase 2: Bulk fill for the Bailey bridge launching platform and the 2nd Rock Groin where the bailey bridge will be launched from. During this phase there will be trucks moving on and off the bulk fill site throughout the day each day. (Timeline: 1 month)

– Phase 3: Installation of the bailey bridge and pedestrian walkway, which will also carry the temporary services. During this phase the traffic flow still remains on existing bridge. (Timeline: 2 months)

– Phase 4: Temporary road installation and once this is completed the redirection of traffic will take place. (Timeline: 1 month)

– Phase 5: Demolition of the existing bridge and preliminary works on the East and Western approaches. (Timeline: 1 month)

– Phase 6: Construction of the new bridge in the same position that the original bridge was on. (Timeline: 3 months)

– Phase 7: Transfer of the services on the new bridge and finishing works (Timeline: 1 month)

– Phase 8: Re-direction of traffic on to the new bridge (Timeline: 1 day)

– Phase 9: Removal of the Bailey Bridge & Temporary Walkway.

– Phase 10: Removal of the rock groins, bulk fills and site reinstatement followed by demobilisation. (Timeline: 2 months Phase 9 & 10)

 

Feedback: waisean@fijisun.com.fj

 


Get updates from the Fiji Sun, handpicked and delivered to your inbox.


By entering your email address you're giving us permission to send you news and offers. You can opt-out at any time.




Five Squares Mad March


Fijisun E-edition
Total
Subscribe-to-Newspaper
Fiji Sun Instagram
Subscribe-to-Newspaper