Energy Fiji Limited (EFL) is ad­vising customers in the Central Division that a new 132kV/33kV Transformer will be installed at the Cunningham Road Zone Substation tomorrow. In order to carry
06 Oct 2018 10:01
EFL To Replace Cunningham Transformer
Energy Fiji Limited

Energy Fiji Limited (EFL) is ad­vising customers in the Central Division that a new 132kV/33kV Transformer will be installed at the Cunningham Road Zone Substation tomorrow.

In order to carry out the installation, EFL Engineers will need to de-energise the 132,000 volts transmission line from the Wailoa Power Station to the Cun­ningham Road 132kV Zone Substation in Suva from 3am to 8pm.

During this outage, EFL will also car­ry out repair and maintenance works on the transmission line from the Wailoa Power Station to Cunningham Road. During this period EFL will rely solely on its Diesel Power Stations at Korovou, Kinoya, Rokobili and Deuba to supply electricity to our Central Di­vision Customers from Matanipusi (Se­rua) to Balekinaga, Tailevu including areas of Deuba, Navua, Suva, Nausori and Korovou.

The available diesel generation capac­ity in the Central Division is not suffi­cient to meet the power demand of all our Customers in the Central Division during this period.

EFL seeks the assistance of our cus­tomers to kindly reduce their electrici­ty usage for the duration of this outage.

EFL also seeks the assistance of our customers who have standby genera­tors at their installations/sites to kind­ly assist by using their generators for the duration of the planned outage.

These works will be undertaken, weather permitting.

Customers in the Central Division may experience power supply outages during the above times.

All queries can be directed to 132 333, Digicel, Inkk and Vodafone users can call us on 5333. For emergencies only, call 913.

Source: Energy Fiji Limited