Mr Prasad said the cost of repairs of the new road amounted to approximately four million dollars.
20 Mar 2021 11:53
Rain Delays Work At Korosomo Slip
Work being carried out on the alternative route for the Koromoso slip on March 17, 2021 in Macuata. Photo: Fiji Roads Authority

There is a possibility that the realignment work at the Korosomo slip in Macuata would be delayed.

Fiji Roads Authority (FRA) Acting Chief Executive Officer Kamal Prasad said the delay was due to the continuous rain in the area that had affected the road progress.

Mr Prasad said the cost of repairs of the new road amounted to approximately four million dollars.

The road was damaged during Tropical Cyclone Ana and upon consultation with the landlords, a new site for the road to be built was agreed.

The alternative route is located a few kilometres away from the slip.

FRA contractors carrying out their inspections on the alternative route for the Korosomo slip on March 17, 2021 in Macuata. Photo: Fiji Roads Authority

FRA contractors carrying out their inspections on the alternative route for the Korosomo slip on March 17, 2021 in Macuata. Photo: Fiji Roads Authority

Mr Prasad said the works were carried out by Kashmir Transport (Sub Contractor) under their FRA Maintenance Contractor, Fairdeal.

He said the new road would have three lanes for motorists.

Edited by Selita Rabuku

Feedback: sampras.anand@fijisun.com.fj



Five Square diwali dhamaka 2021


Get updates from the Fiji Sun, handpicked and delivered to your inbox.


By entering your email address you're giving us permission to send you news and offers. You can opt-out at any time.


Tower Insurance
FNPF
Covid 19 - SPC
Fiji Sun Instagram
Subscribe-to-Newspaper