The weight restriction is 5 TON Gross Weight and vehicle restriction to 4x4s and 3 tonne vehicles.
The Fiji Roads Authority acting chief executive officer, Kamal Prasad stated that FRA was working day and night to c...
“Not all the roads in Tacirua East belong to Housing Authority, FRA is also in charge of some of these roads and w...
“There has been extensive damage on our roads across Vanua Levu and with the number of activities carried out toge...
“FRA is working day and night to complete the much needed work at the earliest opportunity and not wasting taxpaye...
A big road queue awaited commuters from Suva towards Nausori on Thursday evening as they waited for hours while road...
Fiji Roads Authority (FRA) said the shut down is to prevent the controller from getting damaged.
The Main Service Route from Labasa to Savusavu and Labasa to Nabouwalu is still closed to all vehicles.
Several roads across Fiji have become inaccessible due to the adverse weather conditions. Numerous roads, crossings ...
He said requests had been made to the Fiji Roads Authority for the installation of road humps along the old Queen’...
FRA acting CEO Kamal Prasad said these roads were part of its programme but because of the bitumen supply issues, th...
A backup power system has also been installed to keep the traffic signal in operation in case of power outage.
Mr Prasad said rehabilitation works at Waimanu Road that began on December 30 last year were completed last Sunday.
This situation report is to advise of the status of FRA’s assets due to the effect of TC Yasa. Both Queens Road an...
This situation report is to advise of the status of FRA’s assets due to the effect of TC Yasa. Both Queens Road ...
“The upgraded infrastructure will allow the public to be able to travel safely, smoothly and will enhance communit...
Fiji Roads Authority (FRA) is concerned with the repeated acts of vandalism directed at Contractors Plants. This fol...
Fiji Roads Authority (FRA) is pleased to advise that the new Vesidrua Bridge in the Northern Division is completed a...
Residents from the area said the single lane was causing serious traffic issues.
Mr Prasad said all works were done in a manner that no open section of road created traffic during peak hours.
Mr Vakadravuyaca said there were obligations taken on by the Fiji Roads Authority which would need to be completed.
Pratt Street in Suva will be closed for night-works between 7.00pm to 6.00am daily on Thursday 5th and Friday 6th No...
“Works on Nokonoko Road has been postponed to January 2021 due to contractor unavailability,” Mr Prasad said.
This follows after concerns were raised on driver behavior leading to traffic congestion at the
The will continue until April 2020.
The bridge is located along Nabouwalu road between Seaqaqa and Savusavu intersection in the Province of Macuata.
Temporary traffic management will be installed to guide the public around the worksite.
It is not only the traffic signals for vehicles, but there are signs for pedestrians to cross at any time because th...